It applies whether the plant is a bridge until the grid connection arrives, a permanent behind-the-meter supply, or a hybrid with the grid.
1. Fuel: is there enough gas, at the right pressure?
Gas turbine and gas engine plants need firm gas supply at the flow and pressure the machines require. Ask the pipeline operator for available capacity, delivery pressure, gas quality data and the cost and timing of a lateral and metering station. Aeroderivative turbines in particular need high fuel gas pressure, so low line pressure means on-site compression, which adds cost, footprint and a maintenance item.
Check whether the supply can be firm rather than interruptible, and whether a backup liquid fuel or on-site storage is needed for the reliability the tenants expect.
2. Grid: connect, export, or stay islanded?
Even a behind-the-meter plant usually benefits from some grid connection, for backup, start-up power or export. Find out the queue position and study timeline for a connection, the nearest substation capacity and the rules for parallel operation. The answer shapes the plant’s redundancy: an islanded campus needs more spare generation and black-start capability than one with a firm grid tie. Our article on voltage levels for data center builds covers the electrical side.
3. Air permits and emissions
In the USA, a plant of meaningful size will need air permits, and the classification of the area for ozone and other pollutants affects how hard and how long that process is. Engage an air permitting specialist early, run preliminary dispersion modelling and confirm what emissions control will be required. The permit can drive the choice between turbine types and the need for exhaust after-treatment, and it often sets the overall schedule.
4. Water
Gas turbines can run without much water, but evaporative inlet cooling, emissions control by water injection, and some cooling systems for the data halls all need it. Confirm source, quantity, quality and discharge rules. In water-stressed regions, a dry design may be the only acceptable option, and that affects hot-day output.
5. Noise and neighbours
Turbines and engines are loud, and the limits that matter are at the property line and the nearest homes. Map the distances, find the local noise ordinance and allow land for setbacks, enclosures and barriers. Our page on designing out gas turbine noise explains the measures, but they work best when the site gives them room.
6. Climate and altitude
Gas turbine output falls as air temperature and altitude rise. A plant sized on standard conditions will deliver less on the hottest afternoon, which is often when the data hall cooling load peaks. Use local weather records to size for the hot-day case, and decide whether inlet cooling or extra units cover the gap.
7. Land, access and heavy logistics
- Enough area for the generation island, gas yard, switchyard, fuel storage if any, laydown and future units.
- Ground conditions suitable for heavy foundations, confirmed by early geotechnical work.
- A road route that can carry the heaviest packages, with bridges and turns checked.
- Rail or port access for very large components.
- Room to separate the plant from the data halls for safety and maintenance access.
Bringing the shortlist together
Score each candidate site on these seven points and weight them by what cannot be fixed later: gas and permits usually carry the most weight, followed by grid and noise. Then match the shortlisted sites to a generation concept. For US hyperscale developers, one option USP&E is preparing is the New USP&E FX-45 45MW Modular Gas Turbine for the Hyperscale Data Center sector in the USA, alongside remanufactured GE Frame 6B units and hybrid plants. The power build timeline guide shows how site choice feeds the schedule.
About the team behind this checklist
USP&E’s US data center power work is led from Colorado Springs and Knoxville, supported by engineering offices in London, South Africa and China. We work as EPC, EPCM and O&M contractor on power plants, with a record of 150+ power projects in 45+ countries and 25,000 MW contracted since 2002. Read more on our data center power page.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Site selection questions for data center power plants
What is the most important factor when siting a data center power plant?
Usually firm gas supply at adequate pressure, closely followed by air permits. Both are hard to fix after the land is chosen and both drive the schedule.
Does a behind-the-meter data center plant still need a grid connection?
Not always, but a connection helps with backup, start-up power and export, and it reduces the spare generation an islanded campus would need.
How does climate affect a gas turbine plant for a data center?
Hot air and high altitude reduce turbine output, so the plant must be sized for the hottest expected conditions, with inlet cooling or extra units if needed.
How much land does an on-site power plant need?
It depends on the size and technology, but allow for the generation units, gas and electrical yards, setbacks for noise, laydown during construction and space for future units.
Comparing sites for a powered campus?
We can review candidate sites against gas, grid, permits and noise, and outline a generation concept for each.
For a first conversation, use the data center power team, ring +27 10 822 2324 or send the details to info@uspeglobal.com. Available units are listed in the gas turbine inventory on uspeglobal.com.