Building SCR and CO Catalyst Systems into a Data Center Gas Turbine Plant

For many data center campuses planning on-site gas turbines, the air permit decides the shape of the plant as much as the electrical design does. Where nitrogen oxide and carbon monoxide limits are tight, the turbines need catalyst systems in the exhaust, and those systems bring their own steel, chemicals, instruments and schedule.

This guide looks at selective catalytic reduction and CO oxidation catalysts from the construction side: what they need, where they sit, how they affect layout and lead time, and what the owner should settle early so that emissions control does not become the last item holding up first power.

Why the permit drives the catalyst decision

Modern gas turbines with dry low emissions combustors already produce relatively low NOx. In many locations that is enough. In areas with poor air quality, or where the campus total pushes it into a stricter permit class, the regulator may require further reduction that only a catalyst can deliver.

Settle the expected limits before the plant layout is frozen. Adding SCR to a plant that was not designed for it means new ductwork, extra pressure drop on the turbine, more space and possibly a taller stack.

How SCR and CO catalysts work

An SCR system injects a reagent, normally ammonia or a urea solution that converts to ammonia, into the exhaust upstream of a catalyst bed. On the catalyst, the ammonia reacts with NOx to form nitrogen and water vapour. Removal rates of 80 to 90 percent are common when the system is properly tuned.

A CO oxidation catalyst sits in the same exhaust path and converts carbon monoxide and some unburned hydrocarbons to carbon dioxide and water. It needs no reagent, but it adds pressure drop and must be placed in the right temperature zone.

The simple cycle temperature problem

Conventional SCR catalysts work best in a window of roughly 300 to 400 degrees Celsius. In a combined cycle plant, the catalyst sits inside the heat recovery steam generator where the gas has already cooled into that range. A data center plant running turbines in simple cycle has exhaust that is much hotter, often between about 450 and 600 degrees Celsius.

There are two common answers. Tempering air fans blow ambient air into the exhaust to cool it before the catalyst, which adds fans, ducting and power use. Alternatively, a high temperature catalyst formulation can be used, which removes the fans but has its own cost and durability considerations. The choice should be made with the turbine supplier and catalyst vendor together.

Reagent choice and storage

Aqueous ammonia, typically a 19 percent solution, is widely used because it is easier to handle than anhydrous ammonia. Urea is safer still to store and transport but needs a conversion step before injection. Anhydrous ammonia is the most compact but brings the strictest safety and permitting requirements.

Whichever is chosen, the build scope includes an unloading station for tankers, bunded storage tanks, transfer pumps, vaporisation or dosing skids, leak detection and emergency showers. These items interact with the hazardous area classification and with fire and emergency planning for the whole campus.

Layout and structural impact

SCR and CO catalyst housings, injection grids, tempering air fans and transition ducts extend the length of each turbine’s exhaust train. On a site with several units in a row, that adds meaningful width or depth to the power block and can change how close the plant sits to the data halls.

The catalyst housing and ductwork are heavy and need foundations and access platforms for catalyst replacement. Fans and ducts can also add noise at frequencies different from the turbine itself, so update the study described in our guide to gas turbine noise on data center sites.

Continuous emissions monitoring

Most permits that require SCR also require continuous emissions monitoring for NOx, CO, oxygen and often ammonia slip at the stack. The system needs sample probes and heated lines, an analyser shelter with climate control, calibration gas storage and a data acquisition system that reports to the regulator in the required format.

Plan stack ports, platforms and ladders during structural design. Retrofitting sampling ports at height after the stack is installed is slow and expensive.

Schedule, procurement and commissioning

Catalyst modules and SCR housings can have long lead times, especially when many projects are ordering at once. Release the emissions package early, in parallel with the turbine order, and lock the interface points: exhaust flange, temperature, flow and pressure drop allowance.

During commissioning, the SCR is tuned across the load range so that reagent dosing matches NOx at each operating point without excessive ammonia slip. Allow time for this and for the monitoring system certification test. Our overview of gas turbine power plants for data centers shows where these steps sit in the wider programme.

Decisions the owner should settle early

  • Expected NOx, CO and ammonia slip limits, and whether the permit class could tighten as the campus grows.
  • Tempering air or high temperature catalyst, agreed with the turbine supplier.
  • Reagent type, storage volume in days of operation and the delivery route for tankers.
  • Space reserved for catalyst housings on future units, even if early units do not need them.
  • Who owns emissions reporting to the regulator once the plant is running.

What it means for operations

Catalyst systems add reagent deliveries, analyser calibration, injection nozzle checks and periodic catalyst testing to the O&M plan. Catalyst activity declines over the years and the modules are eventually replaced, which needs crane access and an outage window.

Build these into the operating budget and staffing model from the start, so that the plant meets its permit on day one and still meets it years later.

About the authors

This guide comes from the USP&E power plant engineers and construction managers who plan gas turbine installations for industrial sites and data center campuses. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our data center power work covers design, construction and long-term operation.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Gas turbine emissions control questions

Do data center gas turbines need SCR?

Not always. Turbines with dry low emissions combustors may meet the limits alone. SCR is needed where the air permit sets NOx limits below what the combustor can achieve.

What does an SCR system do on a gas turbine?

It injects ammonia or urea into the exhaust ahead of a catalyst, where NOx is converted to nitrogen and water vapour, typically removing 80 to 90 percent.

Why is SCR harder on simple cycle turbines?

Simple cycle exhaust is hotter than the ideal range for conventional catalysts, so the plant needs tempering air fans or a high temperature catalyst.

Which reagent is best for a data center SCR?

Aqueous ammonia is common; urea is safer to store but needs conversion; anhydrous ammonia is compact but has the strictest safety rules.

Does SCR affect the construction schedule?

Yes. Catalyst modules and housings can have long lead times, so the package should be ordered early alongside the turbines.

What is ammonia slip?

It is unreacted ammonia leaving the stack. Good tuning and monitoring keep it within the permit limit.

Plan emissions control early

Share your campus location, expected turbine fleet and permit assumptions, and our engineers will help you define the emissions control scope before layout is fixed.

You can reach the engineering desk on +27 10 822 2324, send drawings or data sheets to info@uspeglobal.com, or leave the details on the data center power enquiry form. Available units are listed in our gas turbine inventory.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · Data Center Build is part of USP&E

Leave a Comment

Your email address will not be published. Required fields are marked *