Most conversations about a data center power plant start with turbines, transformers and permits. The projects that run late often stumble on something duller: nowhere to put the equipment when it arrives, or no reliable electricity for the cranes, welders and cabins that build the permanent plant. Laydown space and construction power are temporary works, yet they set the pace of everything that follows.

This guide walks through how to plan both for a gas turbine plant serving a data center campus. It is written for owners, construction managers and planners who want to avoid the usual surprises: congested access roads, equipment stored in the wrong place and a temporary supply that cannot carry the first big test.

Why temporary works deserve their own plan

A turbine plant brings a long list of large, delicate items to one site within a short window: generator sets, enclosures, step-up transformers, switchgear rooms, pipe spools, stack sections and heat recovery or cooling equipment where fitted. Each arrives on a different transport, with its own storage and handling needs. Without a plan, deliveries are placed wherever there is room, and then moved twice.

Construction power has the opposite problem. It starts small, for site cabins and lighting, and then grows week by week as welding, hydrotesting, cable pulling and eventually commissioning loads arrive. A supply sized only for the first month will limit the third. Treating both as designed systems, with drawings, owners and approval gates, costs little compared with a week of stalled crews. The critical path for data center power shows where these enabling works sit among the permanent activities.

Zoning the laydown area

Good laydown planning begins with a simple zoning drawing. Mark the permanent footprint, the crane paths, the turning circles for long loads and the exclusion zones around buried services and the fuel gas route. What remains is usable laydown, and it should be divided by purpose rather than by contractor.

  • Receiving and inspection zone near the gate, where deliveries are checked against packing lists and any transit damage is recorded before the carrier leaves.
  • Covered, dry storage for electrical gear, instruments and controls, with temperature and humidity limits taken from the manufacturers.
  • Open storage for pipe, structural steel and cable drums, raised off the ground and drained.
  • Heavy-item staging within the reach of the main crane, with ground bearing capacity checked for the loaded wheel or outrigger pressures.
  • Fabrication and prefabrication area, kept apart from storage so cutting and welding do not mix with sensitive equipment.

Plan the sequence as well as the space. Items needed in month two should not be buried behind items needed in month eight. A short matrix linking each major delivery to its storage zone, its lifting plan and its installation date is easy to maintain and makes site meetings quicker.

Storage rules that protect equipment

Turbine and generator makers publish storage requirements, and the warranty usually depends on following them. Rotating equipment often needs periodic rotation, desiccant checks and sealed openings. Electrical equipment may need space heaters energised while it waits, which means the laydown area needs a small but dependable power supply of its own.

Write the rules once and display them at the storage area: who may open a crate, how openings are re-sealed, how humidity indicators are read, and where each inspection is logged. A tidy storage log is also useful evidence later, when someone asks whether a transformer sat in the rain for a fortnight. Records of this kind feed straight into the inspection and test plan for the campus build.

Sizing temporary construction power

Start from the load list, not from the nearest available feeder. Add the site offices and cabins, lighting, small tools, cranes with electric drives where used, welding sets, concrete and pump equipment, hydrotest pumps, and the early commissioning loads such as lube oil systems, battery chargers and heating. Apply realistic diversity factors, then build in headroom for growth.

A simple worked example shows the logic. If cabins and lighting need around 150 kVA, welding machines around 300 kVA connected with a diversity of 0.5, and test and commissioning equipment another 400 kVA, the demand is roughly 150 + 150 + 400 = 700 kVA. Round up for starting currents and growth and choose a supply, transformer and distribution board set that can be extended rather than replaced. These numbers are illustrations of the method, not a design.

Decide early whether the supply comes from a utility connection, from temporary generator sets, or from a staged mix. Utility connections can take time to arrange, so many owners run on temporary generation first and switch over. Whichever route is chosen, the earthing, protection and cable ratings of the temporary system must meet the same safety rules as permanent work.

Distribution, lighting and safety on site

Temporary distribution works best as a ring or radial scheme of marked, lockable boards with residual current protection on final circuits. Cables laid across roads need protection from vehicles, and those run overhead need clear heights for transport of tall items. A single-line diagram of the temporary system, kept current as it changes, is as valuable as the one for the plant.

Lighting is more than comfort. Night work on lifts, pipe testing and cable pulling needs adequate illumination at working height and along walkways, and the layout should avoid shadows behind equipment. Emergency lighting and a clear muster plan complete the picture. Site selection choices made earlier, covered in our site selection checklist, influence how much of this infrastructure has to be built from scratch.

From temporary to permanent supply

The handover between temporary and permanent power is a milestone to plan, not a switch to throw. Permanent switchgear, protection and controls must be inspected, tested and energised in a defined order, with the temporary supply kept available until the permanent system proves it can carry the load. Removing the temporary supply too soon can stop work that is still under way.

Plan the order of energisation, agree who holds the permits, and keep a short list of loads that move over first. Once the permanent supply is live, strip out temporary boards methodically, update the as-built drawings and recover cable for reuse. The same discipline that governs the plant itself should govern its scaffolding, and our wider notes on building a campus power plant explain how these steps connect.

About the authors

This guide comes from the USP&E construction planning team that sets up site logistics and temporary supplies on campus plant builds. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our approach to generation for compute campuses is set out on our page on power for data centres.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Laydown and construction power questions

How much laydown area does a gas turbine plant need?

It depends on the number and size of units and on how deliveries are phased. Plan from a zoning drawing of the permanent footprint, crane paths and storage needs, rather than from a rule of thumb.

What loads does temporary construction power serve?

Cabins, lighting, small tools, welding, concrete and pumping equipment, hydrotest pumps, space heaters for stored equipment and the first commissioning loads.

Should construction power come from the grid or generators?

Either can work. A grid connection may take time to arrange, so many projects start on temporary generators and move to a utility or permanent supply once it is ready.

Why does stored equipment need power?

Many electrical items need space heaters to stay dry and some rotating equipment needs periodic turning, so the storage area needs a reliable small supply.

When should temporary power be removed?

Only after the permanent supply has been energised, tested and shown to carry the site load, with the handover sequence agreed in advance.

Who owns the laydown plan?

Normally the EPC contractor’s construction manager, working with the owner’s site team and the equipment suppliers so each delivery has a place and a lifting plan.

Plan your site enabling works

Send the site plan, equipment delivery schedule and load list for your campus power plant, and our construction engineers will review laydown zoning and temporary power sizing with you.

You can reach the engineering desk on +27 10 822 2324, send drawings or data sheets to info@uspeglobal.com, or leave the details on the construction planning enquiry. Turbine generator packages for campus plants are listed in our gas turbine inventory.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · Data Center Build is part of USP&E

Leave a Comment

Your email address will not be published. Required fields are marked *